The public procurement rules in the Republic of the Congo
In the Republic of Congo, public procurement is governed by the public procurement code (decree no. 2009-156 of 20 May 2009), amended in October 2023, and by 2009 decrees on thresholds, approval and the procurement bodies, which have also been revised since. Amounts are in F CFA excluding tax: national open tendering starts at 50 million for works and supplies and at 10 million for intellectual services. Below that, the buyer must put at least three bidders in competition. Each buyer acts through its public procurement management cell (CGMP); the DGCMP checks before award; the ARMP regulates, publishes the official procurement bulletin and rules on appeals. To bid you need the ARMP's certificate of non-exclusion. The tender file is bought in cash at the CGMP and the bid is filed in a sealed envelope at its address: the online filing platform provided for by a 2024 decree is not in service yet.
Republic of the Congo edition: the rules shown are this country's.Change country
The texts in force
Congo is a member of CEMAC (Central African Economic and Monetary Community), not of UEMOA. CEMAC regulation no. 06/09-UEAC-201-CM-20 of 11 December 2009, which the ARMP summarises on its site, sets the procurement procedures of CEMAC's own institutions and bodies, with a community preference; it is not a code for Congolese buyers. The 2024 decree on electronic procurement also cites a CEMAC regulation no. 009/24-UEAC-001-CM-SE on the Community's procurement. In practice, some Congolese notices announce a preference margin for supplies made in CEMAC states; its rate is in the tender file.[14][11][20]
Décret n° 2009-156 du 20 mai 2009 portant code des marchés publics
The code: bodies, preparation, procedures (open, restricted, design-contest and two-stage tenders, intellectual services, direct agreement, public service delegation), advertising, filing, opening, evaluation, award, guarantees, payment, appeals and sanctions. It replaces decree no. 82/329 of 22 April 1982. Its articles 2, 3, 4, 7, 11, 22, 96, 97 and 137 were rewritten in 2023.[1][2][14]
Partly amended by more recent texts.
Décret n° 2023-1732 du 12 octobre 2023 modifiant et complétant certaines dispositions du décret n° 2009-156 du 20 mai 2009 portant code des marchés publics
Sets three principles that apply whatever the amount (free access, equal treatment, transparency), redefines the major works entrusted to the DGGT, requires contracts to be registered with the ARMP after their registration with the tax office, sets the notification rule and makes a contract void if work has not started within two years of its notification. Its first article lists articles 2, 3, 4, 11, 22, 96 and 137, but the text also rewrites articles 7 and 97.[2]
Décret n° 2009-162 du 20 mai 2009 fixant les seuils de passation, de contrôle et d'approbation des marchés publics, modifié par le décret n° 2011-843 du 31 décembre 2011 et par le décret n° 2023-1734 du 12 octobre 2023
All thresholds, excluding tax and in F CFA (art. 2). The national and international tender thresholds (arts. 10 and 11) and the expression-of-interest threshold (art. 12) have not changed since 2009. The articles on contracts below the thresholds (art. 9), the DGGT (art. 13), DGCMP control (art. 14) and approval (arts. 17 and 18) were rewritten in 2011 and again in 2023: only the 2023 version applies (see the table).[3][4][5]
Partly amended by more recent texts.
Décret n° 2009-160 du 20 mai 2009 fixant les modalités d'approbation des marchés publics, modifié par le décret n° 2023-1733 du 12 octobre 2023
What approval is, the file sent to the approving authority, time limits and the effect of a refusal. The 2023 amending decree is listed by the ARMP but was not read: the points of this decree cited here are the 2009 ones.[6][14]
Partly amended by more recent texts.
Décret n° 2009-157 du 20 mai 2009 portant attributions, organisation et fonctionnement de l'autorité de régulation des marchés publics, modifié par le décret n° 2025-90 du 1er avril 2025
The ARMP, its regulatory council, its disputes committee (appeals and sanctions) and its directorate. The 2025 version gives it electronic procurement and the exclusion list used to issue the certificate of non-exclusion, rewrites the form of appeals and has the committee's decisions published on the ARMP website. It also cites decree no. 2024-2073 attaching the ARMP to the Prime Minister.[7][8]
Partly amended by more recent texts.
Décret n° 2009-159 du 20 mai 2009 (direction générale du contrôle des marchés publics) et décret n° 2009-161 du 20 mai 2009 (cellule de gestion des marchés publics), ce dernier modifié par le décret n° 2022-1854 du 12 octobre 2022
DGCMP prior control and its time limits; each buyer's CGMP, procurement commission and analysis sub-commission. The 2022 amending decree on the CGMP is listed by the ARMP but was not read.[9][10][14]
Partly amended by more recent texts.
Décret n° 2024-2072 du 11 octobre 2024 fixant les conditions et les modalités de la dématérialisation des procédures de passation des marchés publics et de délégations de service public
The electronic procurement system (e-GP) run by the ARMP: registration, electronic signature, encrypted and time-stamped filing, backup copy, online opening and evaluation. It provides for two phases, the second covering exchanges with candidates, and for paper and electronic procedures to coexist until an exclusive system exists. In September 2026, the ARMP was still preparing the tender file to procure that system.[11][15]
Loi n° 3-2000 du 1er février 2000 fixant les conditions d'exercice de la sous-traitance en République du Congo
Subcontracting in every sector: subcontractors established in Congo, priority to Congolese firms, 30% of subcontractors' capital reserved to nationals, and 50% of subcontracting reserved to nationals in contracts of public services, local authorities and public enterprises and establishments.[12]
Loi n° 31-2012 du 11 octobre 2012 déterminant les infractions et les peines applicables en matière de passation et d'exécution des marchés publics
The criminal offences: non-performance after being paid, insider dealing, false inspection reports, handling of the proceeds. Prison or forced-labour sentences and fines of at least double the sums involved.[13]
Textes listés par l'ARMP et non lus: décret n° 2022-111 du 18 mars 2022 et décret n° 2023-1735 du 12 octobre 2023 (délégation générale aux grands travaux), décret n° 2024-2073 (rattachement de l'ARMP au Premier ministre), loi n° 9-2022 du 11 mars 2022 (corruption)
Related texts that the ARMP's “Cadre juridique” page publishes. Their content is not covered here.[14]
Status to confirm with the regulator.
The bodies
ARMP (Autorité de régulation des marchés publics)
Independent regulator with a three-way make-up (administration, private sector, civil society). It publishes the official procurement bulletin, issues the certificate of non-exclusion and keeps the exclusion list, rules on appeals through its disputes committee, sanctions firms and has contracts audited after the fact. It runs the future electronic platform. Office: 25th floor, Tour Nabemba, Brazzaville; contact@armp.cg.[1][7][8][15]
Comité de règlement des différends de l'ARMP
Six members of the regulatory council. As a disputes commission it rules on candidates' appeals and can suspend the procedure; as a disciplinary panel it imposes exclusions and penalties. Its decisions bind the buyer and are published on the ARMP website.[1][7][8]
DGCMP (Direction générale du contrôle des marchés publics)
Part of the finance ministry. Prior control: opinions on tender files and on awards above the thresholds, lighter control below, authorisations (restricted tender, direct agreement, emergency period, two-stage tender, amendments, consultation after an unsuccessful tender). It answers within 10 days of acknowledging receipt, or 15 days if the file goes to a committee; its silence counts as approval.[1][9][5]
CGMP (cellule de gestion des marchés publics) et PRMP (personne responsable des marchés publics)
Each buyer has its CGMP: it plans, drafts the file, publishes the notice, sells the file, receives bids and follows performance. The PRMP heads it, chairs the procurement commission, runs the procedure and signs the contract. Notices name it for questions and for filing.[1][10][20]
Commission de passation des marchés et sous-commission d'analyse
The commission, chaired by the PRMP, opens bids in public session and proposes the award. The analysis sub-commission (a chair and three members, two of them technical staff of the buying entity) evaluates and ranks the bids.[1][10]
DGGT (Délégation générale aux grands travaux)
Mandatory delegated contracting authority for public infrastructure works for national development above 2 billion F CFA. It awards and manages these contracts for the ministries, which remain involved. It publishes its calls for expressions of interest in the bulletin.[2][5][20]
Autorités d'approbation
A signed contract is only valid once approved by an authority other than the signatory: the President of the Republic above 2 billion F CFA, the Prime Minister from over 1 billion to 2 billion, the finance minister up to 1 billion, the planning minister for the finance ministry's own contracts.[1][6][5]
Bulletin officiel d'annonces des marchés publics (BOAMP)
The procurement journal kept by the ARMP. It comes out on Wednesdays, every one to two weeks in 2026. It publishes annual procurement plans, tender notices, calls for expressions of interest and declarations that a tender was unsuccessful.[1][19][20]
Portail des appels d'offres de l'ARMP
Online list of open notices with the buyer, contract type, closing date and the bulletin issue where the notice appeared. It does not receive bids.[18]
Where to find notices
Bulletin officiel d'annonces des marchés publics (armp.cg, rubrique Publications)
Each issue as a PDF (no. 319 of 18 November 2026, no. 318 of 4 November, no. 317 of 21 October...). The full text of each notice: subject, lots, CGMP address, file price, deadline date and time, place and time of opening, bid security, bid validity.
Free download on the bulletin page. The printed issue costs 1,500 F CFA; 3, 6 or 12-month subscriptions are paid at the ARMP office (cash or certified cheque).
Portail des appels d'offres (armp.cg)
Table of open notices, filterable by contract type and buyer, with the number of days before closing.
Free to read. The “Acheter le BOAMP” form on this page shows payment numbers that look like placeholders (checked 26 November 2026): use the free PDF on the bulletin page, or pay at the ARMP office.
Legal texts, standard tender files (works, supplies, services, intellectual services), evaluation guides and forms, directory of certified firms, list of documents for the certificate of non-exclusion, excluded firms, appeal decisions.
Open. Texts download from the “Cadre juridique” page; they are scans.
Cellule de gestion des marchés publics de l'acheteur
Where you consult and buy the tender file, ask questions and file the bid. The notice gives the address, opening hours, phone and often an e-mail address.
The file is paid for, in cash, non-refundable: 100,000 to 125,000 F CFA per lot in the November 2026 notices, up to 300,000 F CFA in a restricted tender of June 2026.
Plateforme de dématérialisation (e-GP), prévue
The single online procurement portal provided for by decree no. 2024-2072: firm registration, online file, encrypted filing, alerts. It is not in service: on 22 September 2026 the ARMP announced that a consultant had prepared the tender file to procure it.
Nothing to do for now. When it opens, filing will require an electronic certificate and a password.
Presse et sites officiels
The code requires the notice to be placed in a national or international publication and electronically, possibly also by posters. Annual plans refer to the bulletin “and other widely read newspapers”.
Who buys
- The State: ministries and institutions of the Republic
- Each ministry buys through its CGMP, under its PRMP (art. 11 of the code). It publishes an annual procurement plan notice in the bulletin early in the year, then one notice per contract. National thresholds in the table; approval by the finance minister, the Prime Minister or the President depending on the amount. Infrastructure works above 2 billion F CFA go through the DGGT.[1][2][5][20]
- Departments and municipalities
- The president of the departmental council or the mayor awards contracts (art. 11 of the code), with the same thresholds as the State: the thresholds decree sets no separate amount for local authorities. Two rules are their own: they may pay SMEs located in their area faster (art. 125), and a foreign bidder subcontracting at least 30% of the contract to a national firm can get a preference margin of up to 5% there (art. 118).[1][3]
- Public establishments, agencies, offices, universities
- The director general awards contracts through the establishment's CGMP (art. 11). The code covers bodies set up by the State or local authorities whose activity they finance or guarantee (new art. 4). The Université Denis Sassou-N'Guesso, the civil aviation agency or the Caisse congolaise d'amortissement thus publish their notices in the bulletin.[1][2][20]
- Public enterprises, majority state-owned companies and private persons funded by the State
- Their contracts follow the code when awarded on behalf of, funded by or guaranteed by a public body; the private person is then treated as a contracting authority (new art. 4). The chairman, managing director or manager awards contracts (art. 11).[1][2]
- Externally financed projects
- Contracts awarded under a financing agreement or treaty follow the code insofar as it does not contradict the agreement (art. 5). When the agreement provides for the funder's rules, those apply, and the file says so. The ARMP also publishes the World Bank procurement regulations (February 2025 edition) on its site.[1][14]
The procedures
Open tender, national (AON) or international
The rule: any other method must be exceptional and justified (art. 28 of the code). Any candidate meeting the conditions may bid (art. 31). National tender from 50,000,000 F CFA excluding tax for works and supplies and 10,000,000 F CFA excluding tax for intellectual services; international from 2,000,000,000 F CFA excluding tax for works and 500,000,000 F CFA excluding tax for supplies and services (decree no. 2009-162, arts. 10 and 11). Prequalification may come first for large or complex works or equipment and for specialised services (art. 32). It is only valid if at least one compliant bid was received (art. 30).[1][3]
Minimum period: The notice appears at least 30 days before the deadline (art. 31). Above the thresholds, the receipt period may not be shorter than 30 calendar days from publication of the notice, even when the notice and file are sent electronically (art. 47). In a duly justified emergency that does not call for immediate action, the DGCMP may authorise 20 calendar days (art. 48).[1][9]
For you: Count from the day the notice appears in the bulletin, not the date the PRMP signed it. Opening takes place one hour after the deadline: a late bid is not accepted.
Restricted tender (AOR)
Only the candidates the buyer chose to consult may bid, in sufficient number for real competition; the rest runs like an open tender. It requires the DGCMP's opinion and one of the listed cases: unforeseeable compelling urgency (natural or technological disaster), an unsuccessful tender, research, testing or development contracts, work done at a defaulting contractor's cost, services only a limited number of firms can provide (art. 37 of the code). Above 25,000,000 F CFA, a call for expressions of interest is published to draw up the shortlist (decree no. 2009-162, art. 12).[1][3]
Minimum period: The same 30-calendar-day minimum as the open tender above the thresholds (art. 47). If fewer than two bids arrive, the procedure is declared unsuccessful and a new period of at least 15 working days is opened and made public (art. 59).[1]
For you: Watch for calls for expressions of interest in the bulletin: they are often the only way in. Check the form required for the bid security: a June 2026 restricted tender asked for a certified cheque or a banker's cheque.
Competition among at least three bidders (below the thresholds)
Below the national tender thresholds, the procedures of article 28 of the code do not apply. The buyer must still put at least three bidders in competition; the contract goes through DGCMP prior control; the award is published by the ARMP (decree no. 2023-1734, new art. 9). The 2009 decree spoke of “comparing at least three invoices” (art. 10). The ARMP publishes standard request-for-quotation files for works and supplies, and a standard purchase-order file for services.[5][3][1][17]
For you: No public notice is required: the buyer picks the three firms. Make yourself known to the CGMPs in your field and keep your administrative documents current, as the consultation can be short.
Direct agreement (gré à gré)
Awarded without a tender, after special prior authorisation by the DGCMP on a report from the procurement commission (arts. 71 and 74). Exhaustive cases: patent, licence or exclusive rights held by a single provider; technical and artistic reasons; extreme urgency to replace a defaulting contractor; compelling urgency due to force majeure; special defence, security and strategic contracts (arts. 72 and 75). The contractor accepts a check on its prices and must open its accounts (art. 73).[1]
For you: You cannot apply. If you hold a genuine exclusivity (patent, licence, exclusive distributorship), keep written proof ready: it is what justifies the procedure.
Call for expressions of interest and request for proposals (intellectual services)
Studies, works supervision, technical assistance and delegated project management are awarded among shortlisted candidates after a call for expressions of interest (arts. 65 and 66 of the code). Technical proposals are opened and scored first; only the financial proposals of candidates reaching the minimum score are opened, in public session, and the others are returned sealed (art. 66). Methods: combined quality and cost, quality only for exceptionally complex assignments, fixed budget, least cost (arts. 67, 68 and 86). Negotiation is held with one candidate at a time and does not touch unit prices when price counted in the ranking (art. 69).[1]
Minimum period: Invited consultants have at least 30 days to submit their proposal, unless the DGCMP gives an opinion otherwise (art. 66).[1]
For you: No bid security for intellectual services. The expression of interest is written in French; in the 2026 notices read, it is filed as one original and two copies, in a sealed envelope that does not carry the firm's name.
Two-stage tender and tender with design contest
Two stages when the buyer chooses on performance criteria rather than detailed specifications: technical proposals without price, then final technical bids with price on a revised file. It needs a reasoned prior authorisation from the DGCMP (arts. 35 and 36 of the code). The contest is for designing a work or architectural project; a jury at least one third of whom are qualified in the field ranks the entries, the rules set the prizes, and unselected entries are returned (arts. 38 to 40).[1]
For you: In a contest, check in the rules whether the winning design becomes the buyer's property and whether you will be involved in carrying it out: it is written in advance.
Call-off contract and customer contract
Call-off contracts for annual routine supplies whose exact quantity is not known in advance; customer contracts for services ordered as needed. One-year term, renewable once with DGCMP authorisation. The contract sets the minimum and maximum limits, in quantity or value (arts. 63 and 64 of the code).[1]
For you: You commit to the maximum quantity, not to what will be ordered: price with the minimum limit in mind.
Public service delegation (management contract, lease, concession)
The State and local authorities entrust management of a public service to an operator paid from operations. The procedure is validated beforehand by the DGCMP; prequalification is mandatory; selection is by open or two-stage tender, direct agreement remaining exceptional; the award is published with a summary of the clauses (arts. 77 to 83 of the code). Contract thresholds also apply to delegations (decree no. 2009-162, art. 20).[1][3]
Minimum period: At least 45 calendar days between publication of the notice and receipt of submissions (art. 78).[1]
For you: Public-private partnerships fall under a separate law (law no. 88-2022 of 30 December 2022, cited by the 2024 decree), not analysed here.
The thresholds
| Buyer | Contract | Amount | Effect |
|---|---|---|---|
| All contracting authorities under the code | Works | 50,000,000 F CFA excluding tax | National tender from this amount (decree no. 2009-162, art. 10). Below: competition among at least three bidders.[3] |
| All contracting authorities under the code | Supplies | 50,000,000 F CFA excluding tax | National tender from this amount for supplies (decree no. 2009-162, art. 10). The text does not name ordinary services in this line, but applies the same below-threshold rule to them (see gaps).[3] |
| All contracting authorities under the code | Consulting | 10,000,000 F CFA excluding tax | Formal procedure (expression of interest then request for proposals) from this amount (decree no. 2009-162, art. 10).[3] |
| All contracting authorities, below the thresholds above | All | Under 50,000,000 F CFA excluding tax (works, supplies, services) or 10,000,000 F CFA excluding tax (intellectual services) | Outside the procedures of article 28 of the code, but competition among at least three bidders, lighter DGCMP prior control and publication of the award by the ARMP (decree no. 2023-1734, new arts. 9 and 14).[5][3] |
| All contracting authorities under the code | Works | 2,000,000,000 F CFA excluding tax | International tender for works (decree no. 2009-162, art. 11).[3] |
| All contracting authorities under the code | Supplies | 500,000,000 F CFA excluding tax (supply of goods or services) | International tender for supplies and services (decree no. 2009-162, art. 11). No international threshold is set for intellectual services.[3] |
| Restricted tender | All | 25,000,000 F CFA excluding tax | From this amount, a restricted tender is preceded by a published call for expressions of interest to draw up the shortlist (decree no. 2009-162, art. 12).[3] |
| DGCMP prior control | All | Over 200,000,000 F CFA (works), over 100,000,000 F CFA (supplies and services), over 50,000,000 F CFA (intellectual services) | The DGCMP checks the procedure and the award before the decision. Below, it carries out a lighter prior check (decree no. 2023-1734, new art. 14).[5] |
| DGCMP prior review of the tender file | All | Over 400,000,000 F CFA (works), over 300,000,000 F CFA (supplies and services), over 200,000,000 F CFA (intellectual services) | The DGCMP reviews the tender file or request for proposals before it is published (decree no. 2023-1734, new art. 14).[5] |
| Major works delegation (DGGT) | Works | Over 2,000,000,000 F CFA | Public infrastructure works for national development above this amount are awarded by the DGGT, not by the ministry (decree no. 2023-1734, new art. 13). Supplies, services and intellectual services only go there if tied to such a works contract.[5][2] |
| Approval of the signed contract | All | Over 2,000,000,000 F CFA: President of the Republic; over 1,000,000,000 up to 2,000,000,000 F CFA: Prime Minister; up to 1,000,000,000 F CFA: finance minister | Authority that approves the contract, whoever the buyer; the planning minister approves the finance ministry's contracts (decree no. 2023-1734, new arts. 17 and 18).[5] |
The administrative documents
We do not yet have a verified list in the Republic of the Congo. These are the documents asked for almost everywhere: check their exact name and the issuing body in the tender file.
Trade register extract (RCCM)
Almost always asked forGreffe du tribunal de commerce
The extract is issued by the registry of the commercial court for the company's registered office. Registration is permanent, but tender files usually ask for a recent extract. Check with the registry for an up-to-date extract.
Company tax identifier
Almost always asked forAdministration fiscale nationale
The tax identifier is assigned by the tax administration at registration; the certificate is obtained from your local tax office. It is requested in every administrative file. Check that the company name matches the RCCM.
Tax status certificate
Almost always asked forAdministration fiscale nationale
It certifies that the company is current on its tax obligations. Apply at your local tax office or through the tax administration's online service where one exists, once all returns are filed. Check the validity period stated on the certificate.
Usual validity: 3 monthsDetailed guide
Social-security compliance certificate
Almost always asked forCaisse nationale de sécurité sociale
It certifies that the company is registered and current on its social-security contributions. Apply at your social-security fund branch. Settle any overdue contributions before applying.
Usual validity: 3 months
Non-bankruptcy certificate
Almost always asked forGreffe du tribunal de commerce
It is issued by the registry of the commercial court for the company's jurisdiction on presentation of the RCCM. It certifies that no insolvency proceedings are ongoing. Tender files usually require a recent certificate: check the requested age.
Usual validity: 3 monthsDetailed guide
Who can bid
- The following may not bid, and their bids are inadmissible: anyone who has not filed returns or paid taxes, duties and social contributions; anyone in receivership or liquidation; anyone under a ban or forfeiture (penal, tax or customs code); anyone with business ties to a consultant who prepared the file; a company in which the PRMP, a commission member, the DGCMP or the approving authority has an interest; anyone convicted of a procurement offence or excluded by a court or by the ARMP. These rules also apply to subcontractors (art. 53 of the code).[1]
- The ARMP's certificate of non-exclusion attests that a firm is not excluded from public procurement. The ARMP states that it is mandatory for every bid in a public tender in Congo. It is valid for one year. Documents: a request to the ARMP's director general, the tax good-standing certificate (tax directorate), the certificate of non-bankruptcy (commercial court), the CNSS social security registration certificate, the single identification number (NIU), and for works the firm's licence (agrément). The file is filed at the ARMP or sent by post; checking takes 3 to 5 working days. The 2025 decree makes the ARMP keep the exclusion list for this certificate, and the ARMP publishes a directory of certified firms.[15][8][16]
- The buyer asks for the technical capacity set in the file and registration in a trade register (commercial and personal property credit register, trades register); any other requirement must be justified and approved by the DGCMP, and none may shut out SMEs (art. 55). Financial capacity is shown by bank statements or professional liability insurance, balance sheets, turnover for at most the last three years, and the single identification number; the notice says which it uses (art. 56). Only the capacity of the lowest evaluated bidder is examined before award (art. 56). A qualification certificate may be requested, but not as the only proof; pharmaceutical products require WHO or equivalent certification (art. 57).[1]
- Any supplier, service provider or contractor may apply and is entitled to equal treatment (art. 28 of the code); free access, equal treatment and transparency apply whatever the amount (new art. 3). The bid is signed by the bidder or an authorised agent, who may represent only one bidder for the same contract (art. 31). The bidder declares in writing any payment to an intermediary or agent, on pain of rejection (art. 9), and undertakes to respect labour law, collective agreements and sustainable development goals, including at its subcontractors (new art. 137).[1][2]
Joint ventures and subcontracting
- Candidates may bid as a joint-and-several or a several-only group. One member, named lead in the commitment form, represents the others and coordinates. In a joint-and-several group, the single commitment form gives the total amount and all the services owed jointly; in a several-only group it gives the detailed split, and the lead remains liable for each member's work. Bids are signed by all members or by the authorised lead. Membership does not change between prequalification and bid submission. Submitting several bids for the same contract or lot, alone and in a group, is forbidden. A member that does not meet the qualification conditions is rejected (art. 119 of the code).[1]
- Subcontracting (works and services only): the file must allow it, and the buyer accepts each subcontractor and its payment terms; a subcontractor that does not meet the qualification conditions is rejected. The bid states the nature and amount of the subcontracted part. Subcontracting more than 30% of the contract value is forbidden. The contractor remains liable. An accepted subcontractor is paid directly, on request and with the contractor's agreement (art. 118 of the code); if the contractor does not respond, the PRMP serves notice on it and pays the subcontractor 45 days later (art. 134).[1]
- Law no. 3-2000 on subcontracting adds: the subcontractor is a firm established in Congo, with its registered office and management there, except for subcontracting of six months or less or intermittent work (arts. 6 and 7). The main contractor gives priority, where possible, to Congolese-law companies run by Congolese nationals with at least 60% Congolese technical and management staff; at least 30% of subcontractors' capital is reserved to nationals (art. 9). Public services, local authorities, public enterprises and establishments reserve 50% of subcontracting to nationals (art. 11). Payments go through Congolese banks and insurance is taken out in Congo (arts. 14 and 15).[12]
- Notices often spell out group rules. For its road supervision assignments (bulletin no. 305), the DGGT accepts only one application per candidate, alone or in a group, on pain of all being eliminated; the same subcontractor may appear in several. The group attaches its signed agreement or a letter of intent signed by all; otherwise the other members are treated as subcontractors and their references do not count.[20]
Bid security
- A bid security is required when the nature of the services calls for it; never for simple supplies or intellectual services (art. 102 of the code). Its amount is in the file, set by the buyer between 1% and 2% of the estimated contract value; it is released at the latest when it expires (art. 103). It is a bank guarantee, which may be replaced by a cash deposit with the Treasury where the rules do not forbid it (art. 2); guarantees take the form of first-demand bank guarantees or sureties under the OHADA Uniform Act on securities (art. 107).[1]
- In published notices the buyer gives a fixed amount: 500,000 F CFA per lot for a supplies contract of the trade ministry (bulletin no. 319), 1,500,000 F CFA for a fisheries ministry contract (no. 311), 2,000,000 F CFA by certified cheque or banker's cheque in a justice ministry restricted tender (no. 303). Whether the security is present is announced aloud at opening (art. 59 of the code).[20][1]
Submitting bids
- The bid is handed in under closed, sealed envelope bearing the tender number and subject, with no indication of the bidder's identity, on pain of rejection. For intellectual services, the technical and financial proposals go in two separate envelopes. The envelope is filed against a receipt at the place given in the notice; it gets a serial number, date and time of delivery, and is entered in a special register issued by the ARMP (art. 59 of the code). The bid comes with a signed commitment form (art. 31). The tender file is written in French (art. 41).[1]
- The notice states where to consult and buy the file, the place, date and time for filing and opening, how long bids remain binding and the security amount (art. 42 of the code). The file price follows a scale set by the ARMP (art. 31), which receives half of it (decree no. 2009-157, art. 62). In the 2026 bulletins, the file is bought at the CGMP, in cash and non-refundable: 100,000 F CFA (Université Denis Sassou-N'Guesso), 125,000 F CFA per lot (trade ministry), 200,000 F CFA (fisheries ministry), 300,000 F CFA (justice ministry restricted tender). Some CGMPs also hand it over electronically. Bids remain valid for 90 days, sometimes 120.[1][7][20]
- Unless the notice says otherwise, the code allows bids to be sent electronically, and a file put online must also be posted to anyone who asks (arts. 50 and 51 of the code). Decree no. 2024-2072 organises such filing on an ARMP platform: electronic certificate and password (art. 17), encrypted and time-stamped bids with acknowledgment of receipt, only the last bid received counting (art. 34), backup copy on physical media in a sealed envelope marked “copie de sauvegarde” (art. 35). Paper and electronic coexist until an exclusive system exists (art. 56). This platform is not in service: on 22 September 2026 the ARMP announced that a consultant had prepared the tender file to procure it. The 2026 notices all ask for physical filing at the CGMP's address.[1][11][15][20]
Bid opening
- The opening session is public. It is held on the last day of the period, at the hour following the closing time; if that day is not a working day, on the next working day. The PRMP chairs it, before the candidates who wish to attend. It lists the bidders and notes bids that are inadmissible or lack the eliminating documents. Each candidate's name, the amount of each bid and each variant, discounts, and whether a bid security is present are read aloud. The minutes, with the signed attendance list, are published and handed without delay to any bidder who asks (art. 59 of the code); the CGMP decree provides for a copy to be given to all participants at the end of the session (art. 15). A bid arriving after the deadline date and time is inadmissible.[1][10]
- A tender is declared unsuccessful, on the commission's opinion, when there is no compliant bid; the decision is published in the ARMP's procurement journal, then the buyer re-tenders or, with DGCMP authorisation, consults at least three firms (art. 31 of the code). In a restricted or intellectual-services procedure, fewer than two bids lead to a new period of at least 15 working days, after which bids are opened however many there are (art. 59). The bulletin publishes these declarations, for example two tenders with no bid at all declared unsuccessful in October 2026 (no. 318).[1][9][20]
Evaluating bids
- The tender is concluded without negotiation, on objective criteria stated in the file and expressed in money as far as possible: price, lead time, running cost, after-sales service, payment terms and schedule (art. 29 of the code). The contract goes to the compliant bid evaluated as lowest (art. 86); point scoring is allowed for some contracts, such as IT and school textbooks (art. 29). Variants are only considered if the file requests or allows them; otherwise only the lowest base bidder's variant is examined (art. 60). With lots, the file says how the best combination is chosen (art. 24).[1]
- The analysis sub-commission checks the administrative documents and evaluates technical and financial bids within the period set at opening: 30 days at most under the code (art. 61), 15 days at most under the CGMP decree (art. 15). It may ask for written clarifications, which may not make the bid more competitive; the bidder has seven clear days to reply (art. 61). The procurement commission decides within 7 working days of receiving the file (decree no. 2009-161, art. 10), then the DGCMP gives its opinion above its thresholds (art. 17 of the code).[1][10]
Preferences and SMEs
- National firms, meaning any firm with its registered office in Congo, can get a reduction of 7.5% to 10% on their financial bid for works and up to 15% for other contracts. This preference only exists if the file provides for it. The file may also set a quantified preference for categories of firms protected by law, but not on top of the national preference (art. 62 of the code).[1]
- In contracts of a local authority or its establishments, a foreign bidder that subcontracts at least 30% of the contract to a national firm can receive a preference margin of up to 5% (art. 118 of the code). Some 2026 notices announce a preference margin for supplies made in CEMAC states, whose rate is in the file (bulletins no. 304 and 314).[1][20]
Award
- The sub-commission draws up minutes (winner, excluded candidates and reasons, abnormally low bids rejected, subcontracted share), which the commission approves, the DGCMP validates where required, and which are published (art. 87 of the code). The award is notified to the winner; the others are informed and their security returned. The minutes are published or sent to all rejected candidates at the same time as the provisional decision. On written request, the buyer gives within 5 working days the reasons for rejection, the contract amount, the winner's name and a copy of the minutes. It waits at least 15 days after publication before signing, and the appeal must be lodged within that period or the right is lost (art. 88).[1]
- The PRMP signs within 7 days of receiving the draft contract signed by the winner (art. 92), after proving that funds are reserved (art. 94). The contract is then approved by the competent authority within the bid validity period; without approval it is void (arts. 15 and 95). Approval can only be refused for lack of funds, by reasoned decision, and any party may challenge it before the ARMP (art. 95; decree no. 2009-160, art. 14). Until the contract is approved, the winner cannot rely on its clauses; if its bid's commitment period has expired, it may refuse notification by registered letter, and it may claim damages if the administration delayed approval (decree no. 2009-160, arts. 6, 16 and 17).[1][6]
- The contract is registered with the tax directorate, on presentation of the single identification sheet issued by the ARMP, then registered with the ARMP (new art. 96). It is notified within 3 calendar days of signature or approval, by a means that gives a certain date, and takes effect on notification, which in practice is the start order. A final award notice is published within 15 calendar days. A contract on which work has not started within two years of notification is deemed void, save force majeure (new art. 97). No claim is admissible for work done before the contract took effect (art. 98). An amendment is capped at 20% of the base contract and needs DGCMP authorisation (art. 115).[2][1]
Appeals
- First appeal to the person responsible for the contract, whose decision may be challenged before their hierarchical superior; copy of the request to the ARMP. It may target the award or non-award, advertising, participation rules, the capacity and guarantees required, the award method, the file's compliance, specifications and criteria, and must invoke a clear breach of the rules. Time limit: 5 working days after publication of the provisional award decision, or within the 10 working days before the filing deadline if it targets the file. It suspends the award procedure until the final decision (art. 141 of the code).[1]
- Second appeal to the ARMP disputes committee: within 8 working days of notification of the contested decision (art. 142 of the code). If the buyer or the hierarchical superior does not answer within 3 working days, the candidate may go straight to the committee, which must decide within 7 working days, failing which the award can no longer be suspended. The appeal is lodged by hand, by registered letter with acknowledgment of receipt (art. 143) or by any electronic means. The request, addressed to the committee's chair, gives the claimant's name and address, the subject, a short statement of grounds, the supporting documents and, where relevant, the contested decision (decree no. 2025-90, new art. 41).[1][8]
- The committee may correct the breach, order protective measures or suspend the decision or procedure; the buyer must comply immediately (art. 142 of the code). The final award stays suspended until its decision (decree no. 2009-157, art. 37). Its decision may be taken to court, with no suspensive effect. While the committee has not ruled, the court cannot be seized at the same time, unless no decision is given within 15 days (decree no. 2009-157, art. 42). The committee's decisions are published on the ARMP website (decree no. 2025-90, new art. 34).[1][7][8]
- During performance, a contractor in disagreement with the PRMP goes to its hierarchical superior for an amicable settlement. Without agreement within 30 calendar days, the dispute goes to the courts or arbitration provided for (arts. 144 and 145 of the code). The ARMP may give opinions in this amicable settlement (decree no. 2009-157, art. 37).[1][7]
Performance guarantee
- A performance guarantee is due for any contract whose performance exceeds six months, except intellectual services (art. 104 of the code). The PRMP sets its amount, at most 5% of the base price plus or minus amendments (art. 105). It is released within a month of the end of the guarantee period or, if there is none, on acceptance (art. 106). Faced with an abnormally low bid, the commission may require a higher guarantee; the bid is only rejected if the candidate refuses (art. 91).[1]
Advance payment
- The start-up advance is capped at 30% of the initial contract for works and intellectual services, and at 20% for supplies and other services. It is only paid against a bank guarantee of equal amount (art. 121 of the code). It is always provided for in the file; above 5% of the contract it is guaranteed up to its amount (arts. 108 and 122). It is repaid at the pace set by the contract, by deduction from instalments and the balance (art. 123).[1]
Retention
- When the contract has a guarantee period, the buyer may withhold part of each payment to cover completion of defects. The retention does not exceed 5% of payments and its rate is set in the specifications (art. 110 of the code).[1]
Payment
- Payments are made by transfer to an approved bank or by documentary credit; changing bank details requires an amendment and a release letter from the former bank (art. 120 of the code). Work started gives a right to instalments, optional for a contract under three months (art. 124). Instalments and the balance are paid within 90 days at most; local authorities may pay SMEs based in their area faster (art. 125). Late payment attributable to the buyer gives a right to default interest, after formal notice left unanswered for 30 days, from the day after the due date (art. 130). The contract may be pledged under the OHADA Uniform Act on securities (art. 135).[1]
- Late-delivery penalties: at most 0.5% of the price including tax per week, after formal notice left unanswered; the buyer may waive them by reasoned decision, under ARMP control (art. 131 of the code). Total penalties do not exceed 10% of the contract including tax and amendments, otherwise the contract is terminated (art. 132). A contract of one year or less has no price revision (art. 114). A suspension of more than three months, at once or in total, gives the contractor the right to terminate, with compensation (art. 139); it may also terminate for non-payment after formal notice left three months without effect (art. 140).[1]
Sanctions
- The ARMP sanctions a firm that colluded on prices, benefited from contract splitting or steered the file, over-invoiced or falsely invoiced, tried to influence evaluation or award, was found by a court to have defaulted on an earlier contract, or supplied false information or used confidential information. Cumulative sanctions: confiscation of guarantees, exclusion from procurement for up to five years (extended, in case of collusion, to the majority parent or subsidiary), withdrawal of the licence or qualification certificate, a fine. On repeat, a court may impose permanent exclusion. The list of excluded firms is published on the ARMP website (art. 146 of the code). The fine is capped, per breach, at a percentage of the offender's annual turnover (decree no. 2009-157, art. 45; see gaps). A contract obtained by fraud or corruption is void (art. 149).[1][7]
- Under criminal law, anyone who received an advance, instalment or balance on a contract without performing, save force majeure, faces two to five years in prison if the loss is under 50 million F CFA, five to ten years of forced labour from 50 million, and in both cases a fine of at least double the sums involved (law no. 31-2012, art. 2). Supplying confidential information that wins a contract carries the same penalties (art. 4). A legal person found to be the offender or an accomplice is punished with the same fine (art. 8). These sentences cannot be suspended (art. 10). A contractor who knew of a public official's scheme without reporting it is not released from its obligations (art. 3).[13]
Traps to know about
- The ARMP certificate of non-exclusion is required to bid, is valid for one year and takes 3 to 5 working days to check, once you have gathered the tax good-standing certificate, the non-bankruptcy certificate, the CNSS certificate, the NIU and, for works, the licence. Apply before you see the notice, not after.
- The outer envelope must not show your company's name or logo: the code provides for rejection of a bid that reveals the bidder's identity. Write only the tender number and subject.
- The file is paid for in cash at the CGMP and is not refunded. The amount varies from one notice to another: read it before you travel, and keep the receipt.
- The electronic filing platform provided for by the 2024 decree is not in service. File on paper at the notice's address, against a receipt, unless the notice says otherwise. The FAQ on the ARMP site mentions online registration and an online certificate request: that is not what the certificate page describes, which asks for filing at the ARMP or sending by post.
- The thresholds have changed twice. 2009 and 2011 texts still circulate: delegation to the DGGT from 250 million F CFA (2009) or from 1 billion for works (2011), approval by the President or the finance minister only. Since October 2023, the DGGT only takes infrastructure works above 2 billion, and the Prime Minister approves contracts from over 1 billion to 2 billion.
- The appeal period is 5 working days after the provisional award is published, and the 2026 bulletins read publish no awards. After the opening, ask the PRMP in writing for the result and the reasons (it has 5 working days to answer) and send your appeal with a copy to the ARMP without waiting.
- A contract only takes effect once approved and notified. Start nothing before the start order: a claim for work done before the contract took effect is inadmissible.
- The bid security does not always take the same form: some notices ask for a bank guarantee, others a certified or banker's cheque. Read the required form in the notice and the bid data sheet, and allow for your bank's lead time.
- National preference benefits any firm with its registered office in Congo, but only if the file provides for and quantifies it. Check the clause before counting on it in your price.
- Payment is due within 90 days, but default interest only runs after formal notice left unanswered for 30 days. Send it in writing, with proof of receipt, as soon as the deadline passes.
What we could not confirm
Rather than guess, we list here what no reliable source allowed us to confirm. On these points, rely on the tender file or ask the body concerned.
- Three amending decrees listed by the ARMP were not read: no. 2023-1733 (approval), no. 2022-1854 (CGMP) and no. 2023-1735 (DGGT). What is said here about approval and the CGMP comes from the 2009 decrees and may have changed.
- The texts contradict each other on two periods. Bid evaluation: 30 days at most under the code (art. 61), 15 days at most under the CGMP decree (art. 15). Refusal of approval: within 30 calendar days under the code (art. 95), within 10 calendar days under the 2009 approval decree (art. 14), itself amended in 2023 by a text that was not read.
- The 2011 decree exempted contracts under 10,000,000 F CFA, awarded by purchase order, from approval. The 2023 decree rewrote the article containing that sentence without repeating it. So it is not known whether the rule still holds; the ARMP still publishes a standard purchase-order file.
- The national tender threshold (decree no. 2009-162, art. 10) names “works and supplies” and intellectual services, not ordinary services, while the next sentence puts services under the three-invoice rule below the threshold. Applying 50,000,000 F CFA to services is likely but not written. No international threshold is set for intellectual services.
- Uncertain readings in the scans: the cap on the ARMP fine (decree no. 2009-157, art. 45) is read “5 70” by text recognition, probably 5%, without certainty. Law no. 31-2012 was read without its articles 5, 6, 12 and 13, missing from the copy. One line of article 28 of the code (justifying a method other than open tender) is missing from the reading.
- The electronic procurement decree is dated 11 October 2024 in its text; the ARMP's list dates it 10 October 2024. No date has been announced for opening the platform to firms.
- No CEMAC text harmonising national public procurement was found. Regulation no. 009/24-UEAC-001-CM-SE cited by the 2024 decree was not read, and the 2009 regulation cannot be downloaded from the ARMP site (“fichier non disponible”). The rate of the CEMAC preference margin announced in some notices is not known without the file.
- Not established: the ARMP's scale for file prices, the percentage of contract values paid to the ARMP (set each year by the finance law), the fee for lodging an appeal, the cost of the certificate of non-exclusion, the default-interest rate (left to the general administrative clauses), the deadline for providing the performance guarantee and the date the retention is released.
- Law no. 3-2000 reserves 50% of subcontracting in public contracts to nationals, and the code forbids subcontracting more than 30% of a contract. No text read says how the two rules combine, or whether sector implementing rules exist.
- The bulletin states that it publishes award results, but the 16 issues of 2026 whose text could be read (no. 302 to no. 319; two issues are images only) contain none. It is not known where the ARMP currently publishes provisional and final awards.
- The FAQ on the ARMP site gives criteria weights (40% technical, 35% price...), an appeal period of “generally 10 days” and a 5-day certificate period that appear in no text read and contradict the code. They are not used here. The site also shows two addresses (Tour Nabemba, avenue Amilcar Cabral): call before filing a certificate application.
Sources
- Décret n° 2009-156 du 20 mai 2009 portant code des marchés publics, art. 1 à 152 (scan lu par reconnaissance de texte) (ARMP Congo (Autorité de régulation des marchés publics), rubrique Cadre juridique, 2009-05-20)
- Décret n° 2023-1732 du 12 octobre 2023 modifiant et complétant certaines dispositions du décret n° 2009-156 portant code des marchés publics (art. 2, 3, 4, 7, 11, 22, 96, 97 et 137 nouveaux) (ARMP Congo, rubrique Cadre juridique, 2023-10-12)
- Décret n° 2009-162 du 20 mai 2009 fixant les seuils de passation, de contrôle et d'approbation des marchés publics, art. 1 à 21 (ARMP Congo, rubrique Cadre juridique, 2009-05-20)
- Décret n° 2011-843 du 31 décembre 2011 modifiant et complétant certaines dispositions du décret n° 2009-162 (art. 9, 13, 14 et 18 nouveaux) (ARMP Congo, rubrique Cadre juridique, 2011-12-31)
- Décret n° 2023-1734 du 12 octobre 2023 modifiant et complétant certaines dispositions du décret n° 2011-843 (art. 9, 13, 14, 17 et 18 nouveaux) (ARMP Congo, rubrique Cadre juridique, 2023-10-12)
- Décret n° 2009-160 du 20 mai 2009 fixant les modalités d'approbation des marchés publics, art. 1 à 19 (ARMP Congo, rubrique Cadre juridique, 2009-05-20)
- Décret n° 2009-157 du 20 mai 2009 portant attributions, organisation et fonctionnement de l'autorité de régulation des marchés publics, art. 1 à 73 (ARMP Congo, rubrique Cadre juridique, 2009-05-20)
- Décret n° 2025-90 du 1er avril 2025 modifiant et complétant certaines dispositions du décret n° 2009-157 (art. 2, 3, 5, 6, 18, 26, 34, 41, 47, 48, 50 à 53 et 55 nouveaux) (ARMP Congo, rubrique Cadre juridique, 2025-04-01)
- Décret n° 2009-159 du 20 mai 2009 portant attributions, organisation et fonctionnement de la direction générale du contrôle des marchés publics, art. 1 à 32 (ARMP Congo, rubrique Cadre juridique, 2009-05-20)
- Décret n° 2009-161 du 20 mai 2009 portant organisation et fonctionnement de la cellule de gestion des marchés publics, art. 1 à 26 (ARMP Congo, rubrique Cadre juridique, 2009-05-20)
- Décret n° 2024-2072 du 11 octobre 2024 fixant les conditions et les modalités de la dématérialisation des procédures de passation des marchés publics et de délégations de service public, art. 1 à 60 (ARMP Congo, rubrique Cadre juridique, 2024-10-11)
- Loi n° 3-2000 du 1er février 2000 fixant les conditions d'exercice de la sous-traitance en République du Congo, art. 1 à 19 (ARMP Congo, rubrique Cadre juridique, 2000-02-01)
- Loi n° 31-2012 du 11 octobre 2012 déterminant les infractions et les peines applicables en matière de passation et d'exécution des marchés publics (art. 1 à 4, 7 à 11, 14 et 15 lus) (ARMP Congo, rubrique Cadre juridique, 2012-10-11)
- ARMP Congo, Cadre juridique: liste et résumés des textes publiés (dont décrets n° 2022-1854, 2023-1733, 2023-1735, 2024-2073, règlement CEMAC n° 06/09-UEAC-201-CM-20, directive CEMAC n° 6/11-UEAC-190-CM-22, règlement de passation des marchés de la Banque mondiale de février 2025) (ARMP Congo)
- ARMP Congo, page d'accueil: certificat de non-exclusion (définition, validité, procédure, pièces) et annonce du 22 septembre 2026 sur le système dématérialisé (e-GP) (ARMP Congo)
- ARMP Congo, Répertoire des entreprises certifiées (ARMP Congo)
- ARMP Congo, Dossiers types (travaux, services, fournitures, prestations intellectuelles), dont les demandes de cotation et la lettre de commande (ARMP Congo)
- ARMP Congo, Portail des appels d'offres (avis ouverts et dates de clôture, consulté le 26 novembre 2026) (ARMP Congo)
- ARMP Congo, Bulletin officiel des marchés publics: liste des numéros et téléchargement (n° 309 du 5 août au n° 319 du 18 novembre 2026) (ARMP Congo)
- Bulletin officiel d'annonces des marchés publics, n° 302 (27 mai 2026), 303 (10 juin), 304 (17 juin), 305 (24 juin), 311 (26 août), 312 (2 septembre), 314 (23 septembre), 317 (21 octobre), 318 (4 novembre) et 319 (18 novembre 2026) (ARMP Congo, 2026-11-18)
Read next
Ready to try?
The account is free and public tenders stay free. Three minutes is enough to receive the first ones.
Get started free